Cobourg, ON (Issued July 19, 2019 9 a.m. EST) – The Town of Cobourg, in conjunction with Lakefront Utility Services Inc. has included the construction of Kerr Street and reconstruction of Albert Street and Mathew Street in the 2020 budget. Pending Council approval, construction is expected to start in early 2020 for Kerr Street and spring 2020 for Albert Street and Mathew Street.
Work will include new storm sewer, watermain and road reconstruction.
Project limits for each street are as follows:
- Kerr Street from Division Street westerly 400 meters including Midtown Creek Flood Reduction Pond
- Kerr Street from Division Street to D’Arcy Street
- Mathew Street from King Street West to University Avenue West
- Albert Street from Hibernia Street to Third Street
A Public Information Meeting will be held on Tuesday, October 8, 2019 from 5 p.m. to 7 p.m. in the Spoolon room at the Cobourg Community Centre located at 750 D’Arcy Street. Preliminary drawings will be available for viewing and staff from the Town of Cobourg and CIMA Canada Inc. will be on hand to answer questions.
If you are unable to attend but would like to have further information or submit comments, please contact either of the following individuals:
Terry Hoekstra, C.E.T. | Larry Spyrka |
Steve May, C.E.T. |
|